The Federal Energy Regulatory Commission is where many of the decisions shaping America’s transmission system get made — how the grid is planned, how costs are allocated, and how quickly new capacity can come online. ACEG monitors these proceedings closely and files comments in the ones that matter most for transmission expansion.

This page tracks the FERC dockets we’re following. Each entry lays out the proceeding’s activity in chronological order, with links to key filings and orders, including ACEG’s own.

Last updated: July 31, 2026.

Active Dockets

RM26-4 — Interconnection of Large Loads to the Interstate Transmission System

In November 2025, FERC proposed an ANOPR on Interconnecting Large Loads after direction from the Secretary of Energy pursuant to the Secretary's authority under section 403 of the Department of Energy Organization Act. The Secretary requested final Commission action by April 30, 2026.

On November 21, 2025, ACEG submitted comments.

On December 5, 2025, ACEG submitted reply comments.

On April 16, 2026, FERC announced action by June 2026.

On June 18, 2026, FERC released six show cause orders under section 206 of the Federal Power Act to all six regional grid operators.

AD25-4 — NERC Submits the Interregional Transfer Capability Study (ITCS) as Directed in the Fiscal Responsibility Act of 2023

On November 19, 2024, NERC submitted its ITCS to FERC in advance of its December 2, 2024 deadline.

On November 25, 2024, FERC issued its Notice of Request for Comments, which were due February 25, 2025.

On February 25, 2025, ACEG submitted comments.

FERC is required to submit a report to Congress within 12 months of the close of the public comment period (by February 25, 2026), and report its conclusions and recommendations, if any, for statutory changes.

On February 25, 2026, FERC released the ITCS report to Congress.

EL25-109 — Five State PSCs' Complaint Against MISO's LRTP Tranche 2.1

On July 30, 2025, five public service commissions (North Dakota, Montana, Mississippi, Louisiana, and Arkansas) filed a complaint arguing that the benefits of MISO's LRTP Tranche 2.1 are overstated and the resulting cost allocation is unjust and unreasonable. The commissions seek to have the projects declassified as Multi-Value Projects, arguing that MISO's benefits metrics overstate the benefit-to-cost ratio.

On September 9, 2025, ACEG submitted comments.

EL25-49 — Order to Show Cause re PJM and Co-Location

On February 20, 2025, FERC instituted a show cause proceeding under section 206 of the Federal Power Act, directing PJM and its transmission owners to explain why PJM's tariff remains just and reasonable without specific provisions for co-location arrangements, or propose changes if it is found unjust or unduly discriminatory.

This proceeding was consolidated with the November 2024 technical conference and the Constellation complaint on fully isolated co-located loads.

On April 24, 2025, ACEG submitted comments.

On December 18, 2025, FERC issued a draft Order stating that PJM's Tariff was unjust and unreasonable, finding that there was insufficient clarity or consistency in the rates, terms, and conditions of services that apply to generators serving co-located load and eligible customers taking transmission service on behalf of co-located loads.

EL25-44 — Complaint of Industrial Energy Consumers of America, et al.

On December 19, 2024, the Industrial Energy Consumers of America, et al., filed a complaint challenging provisions in tariffs of FERC-jurisdictional public utility transmission providers, including RTOs/ISOs and independent transmission owners, that the complaint claims allow individual transmission owners to plan transmission facilities at 100 kV and above without ensuring these plans are the most efficient or cost-effective for the grid or consumers.

On December 26, 2024, ACEG filed a motion to intervene and request for extension of time.

On January 7, 2025, FERC extended the deadline for answers, interventions, comments, and protests to the complaint until March 20, 2025.

On March 20, 2025, ACEG submitted comments.

AD25-7 — Meeting the Challenge of Resource Adequacy in Regional Transmission Organization and Independent System Operator Regions

On May 30, 2025, ACEG submitted pre-technical conference comments.

On June 4 and 5, 2025, FERC held a commissioner-led technical conference to discuss generic issues related to resource adequacy constructs.

On July 7, 2025, ACEG submitted post-technical conference comments.

RM21-17-000 — Order No. 1920: Building for the Future Through Electric Regional Transmission Planning and Cost Allocation and Generator Interconnection

FERC finalized the rule in a 2-1 vote on May 13, 2024, and the rule was published in the Federal Register on June 11, 2024. The order is effective August 12, 2024, and initially, compliance filings were due June 12, 2025.

FERC responded to requests for rehearing and clarification and issued Order No. 1920-A by a vote of 4-0, largely affirming the original rule but extending the period for compliance, allowing states to request an additional 6 months for engagement and allowing planning to begin up to 2 years after compliance is due. Commissioner Christie concurred with a separate statement itemizing 11 areas in which the Commission gave states additional opportunities for input.

On {{DATE NEEDED}}, FERC responded to requests for rehearing and clarification and issued Order No. 1920-B by a vote of 4-0.

On June 12, 2026, MISO submitted its Order No. 1920 compliance filing to FERC. MISO is asking for its Order No. 1920 planning process to be put in place by June 2028 to allow for a smooth transition from its current LRTP process.

On June 12, 2026, SPP submitted its Order No. 1920 compliance filing to FERC. SPP is asking for an effective date of January 2027 for its proposal to bring its CPP to be more in line with Order No. 1920.

On June 12, 2026, WestConnect submitted its Order No. 1920 compliance filing to FERC. WestConnect plans to start its planning process in January 2028.

EL22-83-000 — Invenergy v. MISO

Invenergy asserts that MISO should incorporate merchant projects in its transmission planning.

On {{DATE NEEDED}}, FERC granted in part and denied in part Invenergy's complaint.

Dormant Dockets

Dormant dockets remain open but have seen no substantive activity in recent months. We continue to monitor them and will move them back to the active list if that changes.

AD23-3 — Establishing Interregional Transfer Capability Transmission Planning and Cost Allocation Requirements

In December 2022, FERC staff hosted a virtual technical conference on how to plan and pay for interregional transmission. Recordings of both days and the final transcript are available on FERC's event page.

On December 20, 2023, Invenergy submitted comments on interregional transfer capability and HVDC technology.

On November 19, 2024, NERC submitted its Interregional Transfer Capability Study to FERC, as required by the Fiscal Responsibility Act, which the Commission docketed as AD25-4.

AD24-9-000 — Innovations and Efficiencies in Generator Interconnection

On September 10 and 11, 2024, FERC held a staff-led workshop to discuss innovations and efficiencies in generator interconnection processes. All interested persons were invited to file post-workshop comments on issues raised during the workshop.

After an extension was granted, comments were due November 14, 2024.

ACEG submitted comments focused on the need to build out the backbone of the grid to reduce interconnection upgrade costs.

EL24-80-000, et al. — Order to Show Cause re Midcontinent Independent System Operator, Inc., et al.

On June 13, 2024, FERC issued an Order to Show Cause after finding that the existing open access transmission tariffs (OATT) of certain RTOs and ISOs were unjust, unreasonable, and unduly discriminatory or preferential because they include provisions for transmission owners to unilaterally elect transmission owner (TO) Initial Funding.

The Commission directed each RTO/ISO to, within 90 days, show cause as to why its OATT remains just and reasonable and not unduly discriminatory or preferential, or to explain what changes to its OATT it believes would remedy these concerns.

On October 8, 2024, the Commission granted an extension of time for interested entities to file responses until October 25, 2024.

AD22-8-000 — Transmission Planning and Cost Management

FERC held a technical conference October 6, 2022.

On December 23, 2022, FERC requested additional comments, due March 23, 2023. ACEG submitted comments and circulated a summary of others' comments.

This issue is one of Commissioner Christie's top three priorities in addressing transmission planning reform, and Chair Phillips and Commissioner Clements mentioned in their concurrence with the transmission planning rule that ROFR would be addressed in this docket.

On March 23, 2023, ACEG submitted comments.

AD22-13-000 — Interregional HVDC Merchant Transmission

Invenergy seeks a technical conference to address how to compensate HVDC transmission for reliability and resilience benefits.

Comments were submitted March 8, 2023.

EL22-78-000 — IECA v. MISO

Industrial customers argue that MISO's long-range plan should be built without regard to state ROFRs. Note that the Supreme Court of Iowa rejected the Iowa state ROFR, calling it "quintessentially crony capitalism."

On February 9, 2023, IECA submitted a supplemental comment.

On December 11, 2023, LSP Transmission Holdings and LS Power submitted comments urging the Commission to preempt state incumbent preference laws.

AD23-5-000 — Roundtable on Environmental Justice and Equity in Infrastructure Permitting

FERC held a roundtable on March 29, 2023, to discuss environmental justice and equity in its jurisdictional infrastructure permitting processes. You can read the final transcript.

On May 15, 2023, ACEG submitted comments.